Project Status
Structure Completed, Plastering finished,
Parking lot works finished, Tile Lying in progress, Plumbing &
Electrical work in progress, Putty works in progress, Door fixing in
progress, HT Cable lying in progress, UPVC Windows installation in
progress.http://newlifestyleproperties.com/project-status.php#status